Sorry, my mistake, I thought that defining a 1 hour lag also prevented the gap to be bigger...
So my needs are only to stick some tasks together, one after the other (with a finish to start link), and to prevent any gap between them.
Let me explain my real life case :
My customer works with a really hot hoven to mold titanium pieces. In their projects, they have three tasks concerning the hoven : warm up the hoven (10 to 20 hours), mold the pieces (5 to 25 hours) and cool down the hoven (5 to 15 hour). We need to keep three tasks, because they're not assigned to the same resources, but there can't be any gap between the three : we can't warm up the monday, mold the thursday and cool down the next tuesday ! ^^
Any idea ?