Hello,
a similar problem to https://newforum.radiantq.com/index.php?topic=119.0 (https://newforum.radiantq.com/index.php?topic=119.0) exists, when a task is moved in a large row. The row must be at least as high as 2 tasks.
(https://s20.directupload.net/images/210908/95bxyd8k.gif)
I will send a sample program to reproduce the issue.
Best regards
-
Hi,
We got your reference sample and looking on this, will update you soon.
Thanks
Raja
-
Hi Jan,
We have fixed the reported issue and sent the fixed version to you in the email. Please take a look at it and let us know if you need further assistance.
Thanks
Raja
-
Raja,
the fix works perfectly.
Thank you.
Best regards